PROJECT PROGRESS
West Gatehouse Wall Rebar Works
West Facade Steel Insttaltion Works
North Facade Glass and Louver Insttaltion Works
East Facade Steel and Shell Cassettes Installation Works
East Side
North Corner
North: USTA and Façade Steel Works
North: Shell Cassette installation Works
North: Stay Cabling Works
North: Façade Steel and Flank Wall installation Works
North: Façade Steel and Flank Wall installation Works
North: Flank Wall installation and USTA Works
West: USTA and Flank Wall Steel Works
Basement-2 East: BHS Erected Truss Works
Precast Yard
Water Tank Building (WTB) Interior
Water Tank Building (WTB) Exterior
Central Plant Building (CPB) Basement Interior
Central Plant Building (CPB) Exterior
Goods Lift Building
Utility Tunnel Interior
West Pier
North Pier and Gatehouse
North Pier Tip
North Pier & Mock-up Area
North Pier & Mock-up Area
Central Processing Area
Central Processing Area – Baggage Handling System Trusses
Central Processing Area
Central Processing Area
Central Processing Area
East Pier
East Pier (Northern Face)
East Pier Tip
Precast concrete arch is ready for installation and it weighs 170 tones.
Installation of the first precast arch in the site on 30/4/2018
The smallest arch is 20 meters and the largest arch is 39 meters.
The total number of precast arches between 804-810.
A centralized water tank which supplies water required for cooling of the terminal building, will have a capacity of 5,200m3 of water storage. Excavation for the facility has been completed.
Construction of Fence Type 1
Steel Structure works of permenant offices completed. Finishing, MEP and external facade works ongoing
PVC Waterproofing works for terminal 2 foundation
One of the initial activities was clearing and grubbing of the construction site, to remove the 200mm of top soil containing organic material. A total of around 2 million m2 area has been cleared and grubbed by February 2017.
Terminal 2 has an overall of 270,000m2 of lean concrete works. This activity has commenced in February 2017 from North wing of the terminal building. First foundation concrete pour is expected to be by end of March 2017.
A 9,500m2 building where all the cooling equipment for the terminal building are installed. Excavation for this facility is commenced in February 2017
Project Sign Board Installed
A 600m2 of temporary offices for MPW has been constructed along with shaded car park and other essential facilities. These have been operational since January 2017.
A temporary Contractor’s office with the facilities like canteen, clinic etc were also constructed.
Terminal Building preparation for foundation Concrete
Concrete Works for Permanent MPW Offices
A utility tunnel connecting terminal 2 with central plant building and water tanks will be constructed. Total length of this utility tunnel is around 3.5km. Excavation has commenced in December 2016.
Demolition activity commenced in November 2016 and construction of fence type 1 has been substantially completed. Total length of fence type 1 is 3.2km, fence type 2 is 6.4km and fence type 3 is 4.6kms.
Excavation for the terminal 2 building has commenced in November 2016. Works includes a total quantity of 1.8mn m3 of earth to be moved.
Site Investigations
Clearing and Grubbing of the Construction Site
Further to the site handover on 28 August 2016, topographical survey, subsurface utility survey and additional site investigations were carried out.
Site Handover